| Future cart path site was stripped of sod |
| Cart path area was excavated |
| Grade stakes with set and string line was put up for cart path edges |
| Forms and base completed |
| All work was done by in-house staff. 30 yards of concrete were poured and finished over 2 days |
| Grade surrounding thew new path was excavated and worked to match the cart path. Sod was laid as the final touch. |
| All bunker faces were sodded following railroad tie removal |
| Drainage that had failed was dug up on select bunkers on the West course and repaired. |
| Fertilizer storage at the maintenance facility was updated for cleanliness, safety, more room, and ease of inventory. This photo illustrates how fertilizer pallets were previously stored. |
| Updated shelving for fertilizer storage |
| Another lightning shelter base was re-leveled. Previously the bricks were very uneven and needed repair. |
| Solid tine aerication was completed for all 31 greens within a two day window |