Tuesday, April 2, 2013

Tee Squaring: Day 1

#2 South  White Tee
Yesterday we began our tee squaring project on the South course.  Sod from around the new square tees was stripped off and prepped for seeding.  Small walk paths remain on each tee for entry/exit points.  These walk paths will be removed and seeded as soon as our other surround areas have been established.  We will be able to complete approximately 1 hole per day for sod removal so the project will go quickly.  Laser leveling will begin in the middle of next week on select tees.

#2 South Gold Tee

Extra sod was removed so shaping could be completed on surrounds