Great progress has been made in the last week with only a few minor setbacks due to weather. 1 North was completed and work began on 1 South. As of today, 1 South is completely done being shaped and the left green side bunker is sodded. The remainder of the hole will be sodded this Monday. Work has also started on 7 South with sod being removed from the green surround and rough shaping of the new bunker. Enjoy the rest of the weekend-
Rough shaping of new bunker left of 1 South green
Left bunker on 1 South green shaped and detailed
Drainage being added to 1 South green side bunker
Ready for Matrix liner and sand on the left green side bunker on 1 South