As we transition into winter we will be pruning trees and completing some organizational improvements to our maintenance facility and its surrounding area. Below are some photos of the projects completed so far and a short description during each process.
Bridge project started by 8 South ladies tee. Concrete base reinforced by 3/4" rod prepped, framed, and poured by in house staff |
Cinder block work completed and stone veneer being installed on the sides. |
Stone caps being mortared in place |
Finished walking bridge! Turf restoration remains to be done in the spring on the bridge surrounds. |
Patio stones removed, area trenched and graded, and new drainage pipe installed by in-house staff |
Connection made to mainline drainage 7' below ground! |
Patio stones being re-installed by Assistant Superintendent Michael Brown and staff |
Concrete pad poured using a contractor. Pad is reinforced with wire mesh, 5/8" rod, and fiber mesh. Concrete was poured 6" thick. |
Blocks being delivered for making walls and partitions |
Setting blocks |
First load of topdressing sand delivered to the new pad |
Walls being built to separate materials |
Back view of the bins from the Jr. Learning Course |
Pond dredging: Years of sediment buildup in the irrigation pond needed to be removed. |
Large bag filling up with muck during the pumping process |
Large pump on the pond edge. This pond at the center is almost 25' deep! |
Not only muck was removed from the center of the pond! |
Divers in the water pumping muck left of 7 north approach |
Irrigation pond between 3 and 7 north from an aerial view getting pumped out |