While coordinating between bad weather days and the architects schedule, we have also started working on 3 South. Topsoil was stripped from the work area and soil moving/shaping started. By the end of next week #3 should be completely shaped and irrigated. Below you will see a few pictures of the renovation work in progress. Enjoy your weekend, and GO GREEN! Unless you're a Wolverine fan....then GO BLUE!
Irrigation heads are measured for perfect spacing and flagged for installation |
New valves are connected to the main line to run lateral lines to 2 and 3 South |
New 3" mainline connected and run to 2 South fairway |
Soil moved around to begin forming the new fairway bunker on 2 South |
Brand new pro tee on 2 South built by in-house staff using the new mini excavator purchased with capital. This tee adds 15 yards to the hole! |
New bunker shaped on the left side of 2 South 35 yards from the green |
Topsoil being redistributed around areas of 2 South where shaping is complete |
Gary from 1st Class Golf dozing into the clay to shape the right side of 2 South |