| Photo by Dave Senator |
![]() |
| Photo by Dave Senator |
![]() |
| Photo by Kathy Fenner |
![]() |
| Photo by Kathy Fenner |
![]() |
| Photo by Dave Senator |
![]() |
| Photo by Dave Senator |
![]() |
| Photo by Kathy Fenner |
![]() |
| Photo by Kathy Fenner |
| Future cart path site was stripped of sod |
| Cart path area was excavated |
| Grade stakes with set and string line was put up for cart path edges |
| Forms and base completed |
| All work was done by in-house staff. 30 yards of concrete were poured and finished over 2 days |
| Grade surrounding thew new path was excavated and worked to match the cart path. Sod was laid as the final touch. |
| All bunker faces were sodded following railroad tie removal |
| Drainage that had failed was dug up on select bunkers on the West course and repaired. |
| Fertilizer storage at the maintenance facility was updated for cleanliness, safety, more room, and ease of inventory. This photo illustrates how fertilizer pallets were previously stored. |
| Updated shelving for fertilizer storage |
| Another lightning shelter base was re-leveled. Previously the bricks were very uneven and needed repair. |
| Solid tine aerication was completed for all 31 greens within a two day window |
| The old cart path with new soil graded in and close to being ready for seed. This area will be seeded in the spring of 2017. |
| Patio pavers underneath the lightning shelters were in poor shape. |
| Pavers were removed. As can be seen in this photo, a sufficient base was not used in the past to keep the pavers from moving. |
| A new stone base was installed and compacted and the pavers were laid back in place. Finish grading and sod is the next step to completing this area. |
| Cart path sinking around disconnected culvert |
| Space can be seen here where the connection should be tight |
| Repaired culvert |
| Stone was compacted all around the pipe for stability |
| New "bridge" was framed and leveled with sand |
| Wire mesh installed for strength and concrete being poured |
| Concrete finished and rebar set for block installation |
| Block being installed on both sides |
| Stone veneer was custom fit piece by piece |
| Thin veneer being applied to the sides |
| Cap pieces added as the final touch |
| New path poured to align properly to the new bridge |
| Four different quotes were collected for our bulk patio supplies order. When the order was placed, all materials were delivered at once to minimize delivery costs. |
| Mother nature didn't always cooperate and frequent rain during excavation made for a muddy project. |
| When all the excavation was complete, the patio shape was re-marked and flagged. Small tweaks were made at this time to ensure the area was properly graded. |
| 6-8" of stone base was added above the soil grade and compacted to provide a firm base for the patio. Doing this minimizes the risk that the patio blocks will ever move. |
| Construction first began with the seating wall that wraps around the back of the patio including the steps. This involved custom cutting some blocks to make the shape needed for our build. |
| Once a level, compacted grade was established, the wall went up fairly quickly. All wall blocks are secured together using construction adhesive. |
| Wall blocks were placed all around the exterior of the patio to allow for less carrying of the heavy block to set them in place. |
| Drainage tile was installed behind the wall to move water away from the patio. Geotextile fabric was also used against the back of the seating wall to prevent the movement of soil through the cracks. |
| Geotextile fabric installed along the back of the wall |
| Before pavers could be laid across the whole patio, a contractor was hired to run the main gas line and electric service into place. |
| The patio build didn't come without it's problems! Weather changed and everything froze. This slowed down the build but in the end did not negatively impact it. |
| The patio paver process moved quickly when the staff helping was trained to take over the leveling process. |
| The fire pit was built into the patio over top of the previously placed gas line |
| Step coping was set in place during the installation of LED lights |
| LED lights highlighting the new seating wall and steps |
| Plumbing of the fire pit was also done by in house staff |
| Finished patio! Great job by all the staff! |